Hong Kong International Airport three-runway system

  • Twitter
  • Facebook
  • LinkedIn
  • Google+
  • Email
Project PDF Query Form
Name *
Company
Email *
Query
Enter keyword specified in image
Captcha

Atkins is working on a major expansion plan for Hong Kong International Airport (HKIA).

We are working with the Airport Authority Hong Kong to implement a three-runway system (3RS), involving construction of a new airport platform north of the existing north runway. Our scope of works includes the design of the ground improvement works, reclamation, seawalls, re-provisioning works and the extension and modification of existing large box culverts. The size of the reclamation will be approximately 650 hectares - about half the current size of the airport platform.

The main challenge of the project is that no dredging of the soft sediments is allowed because of environmental concerns. Our key task is to develop cost-effective methods to strengthen the soft sediments in-situ such that the post-construction settlements are limited to acceptable values. A follow-up field trial will be conducted to confirm the performance of the treated seabed using the Deep Cement Mixing (DCM) technique.

The detailed design will be delivered within a tight schedule to facilitate the anticipated award of the main works contract in 2016. Our services will continue into the construction phase with the provision of design support services.

Upon completion of the 3RS, the expansion plan will allow the airport to handle an additional 30 million passengers a year according to the Airport Master Planning of 2030.

Key facts

Location:
Chek Lap Kok, Hong Kong

Client:
Airport Authority Hong Kong

Size:
650 Ha of reclamation

RELATED SECTORS

RELATED SERVICES

CONTACT

RELATED PROJECTS

  • The southern runway and associated taxiways comprised of a 3.8km long and 60m wide runway, high speed exit taxiways, parallel taxiways and cross airfield taxiways. The aprons are comprised of passenger terminal aprons, a cargo terminal apron, an aircraft maintenance apron and a business aviation apron. The total area of pavements was 2.5 million m2 of which 1.9 million m2 was located on reclaimed land.

    Atkins carried out the Engineering Design from Initial Scheme Design to Detailed Design as well as the design support during construction stage of airfield pavement, airfield and apron oil separation and stormwater drainage systems. Atkins was also responsible for the coordination of all apron and airfield systems including apron floodlighting system, apron fixed ground power system, apron preconditioned air system, aviation fuel system, combined potable water and fire hydrant system, communications systems, ground lighting system and apron/airfield markings.

    Lack of clear specification for the dimension of future generation of aircraft, operational requirements for a wide range of aircraft on airbridges as well as the drainage on reclaimed land presented major challenges to the design.

    The project was carried out from 1994 to 1998 and the Chek Lap Kok Airport was officially opened in 1998.

    China ,

  • Hartsfield-Jackson Atlanta International Airport’s Runway 10-28, also known as the fifth runway, has been called the most important runway in America.

    Atkins provided site preparation, paving and lighting, and construction documentation to bring this new 9,000ft runway to reality, and to alleviate delays at the world’s busiest airport.

    This runway project required over 17.5 million cubic yards of embankment – transported from a local quarry via a five-mile conveyor system – and the crossing of 10 lanes of I-285, resulting in a runway over 60 feet higher than the interstate highway in some locations.

    USA ,

  • The passenger and aircraft movements at HKIA have increased steadily since the original airport’s opening in 1998 and growth is anticipated to further continue. To meet this demand, it was necessary to increase the total number of passenger aircraft parking stands and airbridge served contact stands. Atkins has been involved in various contracts from the concept design phase through to construction phase of the Midfield Concourse (MFC).

    The Midfield Development involved the initial development of the Midfield Area located between the two runways and which includes new taxiway and twenty aircraft parking stands.

    The total area of pavements is 350,000m2. The project included a new “I” shape passenger MFC building, extension of the Automated People Mover (APM) system to service the MFC, including a new APM station underneath the MFC and APM tunnel extension.

    Atkins provided airfield infrastructure and utilities design and construction stage support services, which included the addition of 20 airport parking contact stands.

    Atkins was responsible for the design and construction stage support for the airfield and apron works including airfield pavements, apron oil separation and storm water drainage systems, aviation fuel system, combined potable water and fire hydrant system, communications systems and power infrastructure, and apron/airfield markings.

    Our team worked with the Airport Authority to provide an advance works contract which enabled early operation of six aircraft parking stands to meet the ongoing increased demands of the Airport as well as vacate the construction site as far as possible.

    This allowed the construction activity to be carryout in a streamline manner. Atkins’ design allowed the flexibility of the apron works to be commission by phases in consideration of handover sequence. These allow early release of the apron to ease aircrafts mid and long layover requirements at the HKIA.

    After six years of design and construction, the Midfield Concourse (MFC) at Hong Kong International Airport was opened to serve passengers on 28 December 2015.

    China ,

  • Initial award included the design of new cargo aprons, involving four cargo stands. Subsequently, Atkins was awarded the Cargo Apron Expansion which comprised of eight cargo stands in the existing cargo terminal apron and involved 81,000m2 of pavements. The apron expansion area was adjacent to the operating Taxiway K and Taxilane L.

    From 2000 to 2003, Atkins carried out the Engineering Design from Initial Scheme Design to Detailed Design as well as the construction supervision of airfield pavement, airfield and apron oil separation and stormwater drainage systems, apron floodlighting system, apron fixed ground power system, aviation fuel system, combined potable water and fire hydrant system, communications systems, ground lighting system and apron/airfield markings.

    China ,