An estimated 300,000 vehicles—equivalent to one-tenth of Nevada’s population—traverse the 3.7 mile-long Project NEON corridor stretching from the “Spaghetti Bowl” interchange in downtown Las Vegas to the south along I-15 every day.

With traffic through this freeway corridor expected to double in the next 20 years, the Nevada Department of Transportation (NDOT) prioritized investment in this critical section of infrastructure to meet the needs of the growing resident and tourist populations.

Travelers make 25,000 lane changes per hour in this freeway corridor and as many as 1,400 crashes take place annually. To boost safety, mobility, and accessibility, roadway improvement plans include separation of freeway traffic from arterial traffic, reduced numbers of merging sections, and connection of high occupancy vehicle (HOV) lanes to create a continuous 22-mile stretch from US 95 through I-15. Considered the most important and ambitious project in NDOT’s history, it also accommodates regional economic redevelopment through improved access to downtown Las Vegas and the Resort Corridor.

We serve as lead designer, for design builder, Kiewit Infrastructure West, managing all design and engineering services on this multiphased, multiyear project with responsibilities that include design services for roadway, drainage, bridges and structures, traffic control, signing, pavement marking, landscape, and ITS as well as providing quality control, utility coordination, public involvement, design surveying, and design support during construction.

 

Video courtesy of NDOT

Key facts

Location:
Las Vegas, Nevada

Country/Region:
United States of America

Owner:
Nevada Department of Transportation

Client:
Kiewit Infrastructure West

Details:
- Busiest stretch of highway in Nevada
- 300,000 vehicles travel daily
- Corridor traffic expected to double
  by 2035
- Project likely to reduce travel delays
  by 28 percent
- $110 million annual savings expected
  through increased productivity
- Construction scheduled to start in 2016
- Estimated completion in late 2019 

RELATED SECTORS

RELATED SERVICES

CONTACT

Group

Departments of Transportation:
Jorge Figueredo
Business Development Director
+1 407 806 4573
Email

RELATED PROJECTS

  • Transit options in the Las Vegas Valley are limited to standard bus system serving the entire community and a short monorail system marketed toward the tourists along the Las Vegas Strip. Bus rapid transit (BRT) was selected as the best option for the valley. Completed in multiple phases, the Downtown Connector project is the first BRT project released by the Regional Transportation Commission of Southern Nevada.

    Atkins provided signal design for 10 intersections to accommodate the BRT vehicles, queue jump, and pedestrian access to the shelters. Atkins also provided civil design for the stations through all three phases including utility coordination, right-of-way services, and platform bus turnout design.

    USA ,

  • The Connector is instrumental in relieving traffic congestion in historic Ybor City and improving freight access to the Port of Tampa. It also provides an additional hurricane evacuation route and enhances emergency access for first responders.

    Atkins served as lead engineer on the $426 million project, and as the primary designer of the Connector’s southern portion (80 percent of the overall construction effort). Innovative features include a toll gantry that saves FDOT an estimated $10 million in capital and maintenance costs, and truck-only lanes that provide convenient, exclusive freight access and minimize congestion and safety issues on local roads. The project is also one of the first to use concrete segmental construction and incorporate the new AASHTO Bridge Code. 

    Atkins' ability to mobilize staff in support of this project enabled completion of alternate bridge designs three months early in an aggressive design schedule. Aesthetics also played a key role in the project, with designers making every effort to incorporate the style and character of historic Ybor City. One of the project’s notable features is a “gateway” that evokes the area’s unique, century-old Florida architecture.  

    The project received the Florida Institute of Consulting Engineers (FICE)/FDOT 2014 Outstanding Project Award, FICE 2015 Engineering Excellence Award, American Council of Engineering Companies (ACEC) 2015 National Recognition Award, and American Segmental Bridge Institute (ASBI) 2015 Bridge Award of Excellence (urban bridges category). 

     

    USA ,

  • The Colorado Department of Transportation (CDOT) selected Atkins to help address the immediate need to improve safety and congestion that has plagued this corridor for many years. The Twin Tunnels project widens the lanes of I-70 from Idaho Springs to the base of Floyd Hill and is the first project to add capacity to the corridor in over 20 years.

    After successfully assisting with the concept design in an environmental assessment, CDOT selected Atkins to complete the eastbound tunnel expansion project under a construction management/general contractor delivery system. After the completion of the initial eastbound tunnel, CDOT sole sourced the Atkins team to complete the westbound tunnel. The compressed delivery schedule and complexity of the project required tapping into Atkins’ worldwide expertise in tunnel design, managed lanes, bridge and retaining wall design, highway design, and construction phasing. The team developed creative solutions to maintain traffic flow during construction, mitigate environmental impacts, and increase highway safety and operations.

    The project was named Engineering News-Record (ENR) Mountain States 2016 Best Project in the highways and bridges category (Colorado, Wyoming and plains states).

    USA ,

  • For Douglas County, Colorado, Atkins prepared a federal funding packet to be used to help secure potential federal funds for improvements to the C-470/US 85 interchange in southwest Denver. Specific work elements included preliminary cost estimates, data analysis, and development of a high-end presentation. The analysis included developing the purpose and need for the improvements that included safety, capacity deficiencies, and the regional need for the facility.

    Additionally, Atkins developed a conceptual design for the C-470/US 85 interchange including modifications to upgrade the existing diamond interchange and the addition of loop ramps and fly-over ramps to increase interchange capacity for the 2025 design year. Our scope of work included projecting existing traffic volumes to the 2025 design year and determining lane requirements for the main line and ramps. In addition we surveyed the existing right-of-way and identified of future right-of-way needs.

    USA ,